Residential lots in the Town of Canaan run from a 2-acre minimum in Medium Density Residential (2-acre) up to 10 acres in Agricultural Density (10-acre), across 10 zoning districts in all. Power here is NYSEG territory. The district table below has the setbacks, height limits and coverage - confirm the specifics with the building department at (518) 781-3144 before you rely on a figure.
Looking specifically at an accessory dwelling unit? See ADU rules for Canaan →
Zoning districts
| District | Min lot | Setbacks F / S / R | Max height | ADU |
|---|---|---|---|---|
| Medium Density Residential (2-acre) | 2 ac | 75 / 25 / 25 ft | 35 ft | As of right |
| Medium Density Residential (5-acre) | 5 ac | 75 / 50 / 50 ft | 35 ft | As of right |
| Rural Density Residential (2-acre) | 2 ac | 75 / 25 / 25 ft | 35 ft | As of right |
| Rural Density Residential (5-acre) | 5 ac | 75 / 50 / 50 ft | 35 ft | As of right |
| Agricultural Density (10-acre) | 10 ac | 75 / 50 / 50 ft | 35 ft | As of right |
| General Business | 0.5 ac | 100 / 25 / 25 ft | 35 ft | Special permit |
| General Commercial | 2 ac | 100 / 25 / 25 ft | 35 ft | Special permit |
| Light Industrial | 2 ac | 100 / 25 / 25 ft | 35 ft | Special permit |
| Mobile Homes (2-acre) | 2 ac | 75 / 25 / 25 ft | 35 ft | As of right |
| Mobile Homes (5-acre) | 5 ac | 75 / 50 / 50 ft | 35 ft | As of right |
Medium Density Residential (2-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-1-2 reaches 450 ft back from the road centreline; a building site beyond that is in RA-1-5, with 350 ft of lot width and 50 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Medium Density Residential (5-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-1-5 covers building sites beyond 450 ft from the road centreline; closer in, RA-1-2 applies, with 200 ft of lot width and 25 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Rural Density Residential (2-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-2-2 reaches 450 ft back from the road centreline; a building site beyond that is in RA-2-5, with 350 ft of lot width and 50 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Rural Density Residential (5-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-2-5 covers building sites beyond 450 ft from the road centreline; closer in, RA-2-2 applies, with 200 ft of lot width and 25 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Agricultural Density (10-acre) - Setbacks are measured from the centreline of the travelled or paved road, not from the property line, so a front yard here is not comparable to one measured the usual way.
- RA-4 is a single 10-acre district and does not split by depth from the road.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
General Business - Buildings and structures in C-1 may total no more than 4,000 sq ft of enclosed building area. Where site plan approval is required, the Planning Board determines the minimum setbacks as part of it.
- Setbacks are measured from the centreline of the travelled or paved road, not from the property line.
- The 20% coverage cap counts all uses on the lot together.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
General Commercial - Buildings and structures in C-2 may total no more than 30,000 sq ft of enclosed building area. Where site plan approval is required, the Planning Board determines the minimum setbacks as part of it.
- Boats, vehicles, machinery and building materials may be stored and displayed only in secured, landscaped and buffered areas or open sheds, which count as enclosed building area.
- Setbacks are measured from the centreline of the travelled or paved road, not from the property line.
- The 20% coverage cap counts all uses on the lot together.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Light Industrial - Every use in C-3 is subject to site plan approval and a special permit. Where site plan approval is required, the Planning Board determines the minimum setbacks as part of it.
- C-3 has no limit on enclosed building area and no limit on lot coverage.
- Setbacks are measured from the centreline of the travelled or paved road, not from the property line.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Mobile Homes (2-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-3-2 reaches 450 ft back from the road centreline; a building site beyond that is in RA-3-5, with 350 ft of lot width and 50 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Mobile Homes (5-acre) - Setbacks are measured from the centreline of the travelled or paved road, not the property line. RA-3-5 covers building sites beyond 450 ft from the road centreline; closer in, RA-3-2 applies, with 200 ft of lot width and 25 ft side and rear yards.
- A two-storey dwelling needs at least 1,000 sq ft of living area across both floors above the basement; the 600 sq ft minimum is for a one-storey dwelling's finished first floor.
- A wind energy conversion system may reach 40 ft.
- A lot may hold no more than one single-family dwelling and one accessory dwelling.
Short-term rentals
Short-term-rental status not confirmed. Short-term rental rules in Canaan are not confirmed. The zoning law's silence on short-term rentals is not permission, and a separate STR law had a public hearing in March 2025; ask the Town whether it passed and what applies before counting on the use.
Conditions the code attaches:
- The zoning law treats a bed and breakfast as an owner-occupied single-family dwelling serving no more than ten transient lodgers, with a special permit needed at three or more rooms.
- New York State's 2025 short-term rental registry requires every host to register the unit, regardless of local law.
- Confirm with the Town of Canaan at (518) 781-3144 before listing.
Good to know
- UtilityNYSEG territory.
- Zoning codeTown of Canaan Zoning Laws and Regulations (October 2024), Article V.D: Density Requirements
- Building dept(518) 781-3144
- Last reviewed2026-06-02
Working out a budget? A standard-finish build here runs $202–$265/sq ft , and a conforming lot adds about $15,906 on top - see the full cost to build a house in Canaan, or what an ADU costs here.
Sizing up a specific parcel in Canaan?
Aldo pulls the exact zoning district, setbacks, and build feasibility for any parcel — before you buy. Enter your email to open Aldo and run your free report.
Other Columbia County towns
All Columbia County zoning: Hudson (City) · Ancram · Austerlitz · Chatham · Claverack · Clermont · Copake · Gallatin · Germantown · Ghent · Hillsdale · Kinderhook · Livingston · New Lebanon · Stockport · Stuyvesant · Taghkanic · Chatham (Village) · Kinderhook (Village) · Philmont (Village) · Valatie (Village)
Zoning figures for Town of Canaan are compiled from the municipal code (last reviewed 2026-06-02) and provided for decision-support only - not legal, engineering, or architectural advice. Setback and dimensional standards often carry conditions and exceptions; verify with the building department at (518) 781-3144 before relying on any number. Source: the Offsite / Aldo zoning dataset.