Aldo

Hurley · ADU cost

What it costs to build an ADU in Hurley, NY

800 sq ft ≈ $200k–265k $252–330/sq ft 9 districts Central Hudson

An 800 sq ft accessory dwelling unit in Hurley runs roughly $200k–265k, or about $252–330/sq ft, and that per-square-foot figure sits deliberately above the $206–270/sq ft a full house costs here. An ADU still needs one whole kitchen, one whole bath, its own service panel and its own heating plant no matter how small you draw it, and those costs do not shrink with the floor plan, so they land on half the square footage and push the rate up. Whether the town will let you build one is a separate question from what it costs, and it gets answered parcel by parcel rather than townwide, since the Town of Hurley maps 9 districts that treat accessory units differently from one another, so read the table below as a starting point rather than a verdict.

Check a specific parcel for an ADU in Aldo, free →

ADU cost by size in Hurley

Standard finish, slab on grade, on a flat and clear part of the lot, general-contractor margin included. These are structure costs at Ulster County pricing, before the service and septic work a second dwelling can trigger.

SizeType$ / sq ftEstimated total
400 sq ft Studio $334–$438 $135k–175k
600 sq ft One bedroom $280–$366 $170k–220k
800 sq ft One bedroom, larger $252–$330 $200k–265k
1,000 sq ft Two bedroom $236–$309 $235k–310k

400 sq ft — One room plus a bath. Garage conversions and small backyard cottages land here.

600 sq ft — The most common detached build - a real bedroom, full kitchen, one bath.

800 sq ft — Room for a proper living area. Still a single bath and one kitchen.

1,000 sq ft — About as large as most codes allow an accessory unit to go.

Why the rate is higher than a house

The systems below are priced for an 800 sq ft unit. The middle column is what each system would cost if it simply shrank with the floor plan; the left column is what it actually costs once you account for the equipment a dwelling needs one of regardless of size. The gap between the two columns is the whole reason small builds price the way they do.

System$ / sq ft in an ADUIf it scaled with floor areaFixed per unit
Site work $7–$11 $7 —
Foundation $17–$23 $17 —
Framing $26–$32 $26 —
Envelope - roof, siding, windows $32–$41 $32 —
Plumbing $28–$34 $17 55%
Electrical $19–$24 $13 35%
HVAC $23–$29 $15 45%
Insulation $7–$9 $7 —
Interior finishes $33–$44 $28 15%
Millwork & cabinetry $19–$28 $11 55%

The fixed-per-unit share is a modeling assumption, not a figure from the code: it is our estimate of how much of each system's budget buys equipment a dwelling needs exactly one of - a kitchen rough-in, a bath group, a service panel, a heating plant - and therefore does not shrink when the unit does. Site work, foundation, framing, envelope and insulation are treated as scaling straight with floor area, which understates the premium slightly, because a small building carries more envelope per square foot of floor than a large one.

What the Hurley code says about accessory units

Whether you can build one, and how large, is decided by the district your parcel sits in rather than by the town as a whole. The table shows how each mapped district treats ADUs alongside the lot and setback standards a second unit still has to fit inside. District boundaries and conditions vary, so treat it as a starting point and confirm the district that applies to your parcel.

District Min lot Setbacks F / S / R Max height ADU
A-4 Very-Low-Density Residential 4 ac 50 / 50 / 100 ft 35 ft Special permit
A-2.5 Low-Density Residential 2.5 ac 50 / 50 / 75 ft 35 ft Special permit
R-1 Moderate-Density Residential 0.92 ac 50 / 25 / 50 ft 35 ft Special permit
R-2 Medium-Density Residential 0.92 ac 50 / 25 / 50 ft 35 ft Special permit
H Historical 0.92 ac 50 / 25 / 50 ft 35 ft Special permit
NC Neighborhood Commercial 0.92 ac 50 / 25 / 50 ft 35 ft Special permit
B-1 General Business 0.46 ac 25 / 15 / 50 ft 35 ft Special permit
B-2 Highway Business 1 ac 40 / 20 / 50 ft 30 ft No
I-1 Light Industrial 2 ac 40 / 20 / 50 ft 30 ft No

A-4 Very-Low-Density Residential - In an open space development the Planning Board may allow lots down to 1 acre, at its discretion and not by right, on a tract of at least 25 acres, with the average lot across the subdivision still meeting the district minimum.

  • At least 50% of the site must be left as green space.
  • New construction, and additions over 1,000 sq ft, require a visual assessment under § 210-42.
  • The one-acre floor applies unless the lot is served by central water or sewer, for which no figure is set.
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

A-2.5 Low-Density Residential - In an open space development the Planning Board may allow lots down to 1 acre, at its discretion and not by right, on a tract of at least 25 acres, with the average lot across the subdivision still meeting the district minimum.

  • A mobile home park needs a site of at least 25 acres, with 100 ft to any public street or adjacent property line, 50 ft between mobile homes and 25% of the gross site kept as open space.
  • A mobile home park needs site plan approval, and its density is set by the average-density formula in § 210-38 rather than by a per-lot minimum.
  • At least 40% of the site must be left as green space.
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

R-1 Moderate-Density Residential - The minimum lot drops to 30,000 sq ft with central sewer or water, and to 20,000 sq ft with both; on both the minimum width is 100 ft, the yards fall to 30 ft front, 15 ft side and 30 ft rear, and coverage may reach 25%.

  • With central sewer or water the yards are 40 ft front, 20 ft side and 40 ft rear, on a 125 ft width.
  • At least 25% of the site must be left as green space, 20% with central sewer and water.
  • Side yards for semidetached dwellings are required at the ends of the total structure only (§ 210-18).
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

R-2 Medium-Density Residential - The minimum lot drops to 25,000 sq ft with central sewer or water, and to 12,000 sq ft with both; on both the minimum width is 100 ft, the yards fall to 30 ft front, 15 ft side and 30 ft rear, and coverage may reach 25%.

  • With central sewer or water the yards are 40 ft front, 20 ft side and 40 ft rear, on a 120 ft width, and coverage may reach 20%.
  • At least 25% of the site must be left as green space, 20% with central sewer or water and 15% with both.
  • Side yards for semidetached dwellings are required at the ends of the total structure only (§ 210-18).
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

H Historical - The minimum lot drops to 25,000 sq ft with central sewer or water, and to 12,000 sq ft with both; on both the minimum width is 100 ft, the yards fall to 30 ft front, 15 ft side and 30 ft rear, and coverage may reach 25%.

  • Bulk standards here are those of the R-2 District.
  • Architectural design review is required for exterior changes in this Old Hurley hamlet historic district on Main Street and Hurley Avenue.
  • With central sewer or water the yards are 40 ft front, 20 ft side and 40 ft rear, on a 120 ft width, and coverage may reach 20%.
  • At least 25% of the site must be left as green space, 20% with central sewer or water and 15% with both.
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

NC Neighborhood Commercial - A residence follows the R-1 District: the minimum lot drops to 30,000 sq ft with central sewer or water and to 20,000 sq ft with both, where the width is 100 ft and coverage may reach 25%.

  • A nonresidential use follows the B-1 District, with a 20,000 sq ft minimum lot, a 100 ft width, 25 ft front, 15 ft side and 50 ft rear yards and no more than 25% coverage.
  • With central sewer or water a residence takes 40 ft front, 20 ft side and 40 ft rear yards on a 125 ft width.
  • At least 25% of the site must be left as green space for a residence, 5% for a nonresidential use.
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).
  • With both services a residence takes 30 ft front and rear yards and 15 ft side yards on a 100 ft width.

B-1 General Business - A one- or two-family dwelling follows the R-1 District: 40,000 sq ft with neither central sewer nor water, 30,000 sq ft with one of them, and 20,000 sq ft with both.

  • With neither service a house takes a 150 ft width, 50 ft front, 25 ft side and 50 ft rear yards and no more than 15% coverage.
  • With central sewer or water a house takes a 125 ft width and 40 ft front, 20 ft side and 40 ft rear yards; with both, a 100 ft width and 30 ft front, 15 ft side and 30 ft rear yards.
  • At least 25% of the site must be left as green space for a residence, 5% for a nonresidential use.
  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

B-2 Highway Business - No dwelling is permitted in B2 (210 Attachment 1). At least 10% of the lot must stay green space.

  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).

I-1 Light Industrial - No dwelling is permitted in I1 (210 Attachment 1). At least 10% of the lot must stay green space.

  • On a corner lot the front-yard standard applies to every street-facing yard (§ 210-14).
  • Performance standards under §§ 210-22 and 210-30 apply.
Check my address for ADU feasibility → Free · no account needed to start

Size limits on record in Hurley

Where the code states a size cap, it decides which row of the cost table above actually applies to you. These are the caps recorded for Hurley:

Costs an ADU adds that a house does not

Sizing up a specific parcel in Hurley?

Aldo pulls the exact zoning district, setbacks, and build feasibility for any parcel — before you buy. Enter your email to open Aldo and run your free report.

Building a full house instead?

A standard-finish house in Hurley runs $206–270/sq ft, about $370k–485k at 1,800 sq ft , plus roughly $15,087 for a conforming lot. See what it costs to build a house in Hurley.

ADU cost in nearby towns

ADU cost in Hurley: common questions

How much does it cost to build an ADU in Hurley, NY?

An 800 sq ft accessory dwelling unit in Town of Hurley runs roughly $200k–265k at a standard finish, general-contractor margin included. A 400 sq ft studio runs about $135k–175k. Those are structure costs on an easy site and do not include the septic, water or electrical service work a second unit often triggers.

Why does an ADU cost more per square foot than a house in Hurley?

Because a lot of a dwelling's cost is per dwelling, not per square foot. One kitchen, one bath group, one service panel and one heating plant cost about the same in an 800 sq ft cottage as in a 1,800 sq ft house, so on the smaller unit they get spread over less than half the floor area. That is why an ADU here prices at $252–330/sq ft against $206–270/sq ft for a full house, even though it is the same trades doing the same work.

Are ADUs allowed in Hurley?

Town of Hurley has 9 districts. 7 districts allow ADUs with a special-use permit, 2 do not. Check the specific address with the free ADU checker or confirm with the building department at (845) 331-7474 before you spend money on design.

Can I rent an ADU in Hurley short term?

Short-term rentals allowed with local rules for Town of Hurley. ADU rules and short-term-rental rules are set separately, so a unit you are allowed to build is not automatically one you are allowed to rent nightly. Confirm both before you underwrite the build on short-term-rental income.

ADU costs are modeled estimates in current 2026 dollars at the Ulster County regional index, general-contractor margin included, derived from Offsite's cost engine with a stated adjustment for the equipment a dwelling needs one of regardless of size. They are planning numbers for decision-support only - not a bid, quote, or guarantee, and not legal, architectural or engineering advice. They cover the structure and exclude septic expansion, utility service runs, site work beyond a flat and clear pad, and permit fees. ADU eligibility, size, owner-occupancy and permit conditions in the Town of Hurley vary by district and often carry exceptions this page does not show; zoning last reviewed Apr 2026; verify with the building department at (845) 331-7474 before relying on any answer. Sources: the Offsite / Aldo cost engine and zoning dataset.

Building outside these counties?

Aldo covers 15 New York counties today. Tell us your market and we'll build the zoning + feasibility data for it.