Albany County
Village of Altamont, NY: zoning for new construction
Residential lots in the Village of Altamont run from a 0.23-acre minimum in Residential One Family - 10,000 Sq. up to 0.92 acres in Residential Conservation District, across 13 zoning districts in all. No local short-term-rental law on record - which is not the same as permission. Power here is National Grid territory. The district table below has the setbacks, height limits and coverage - confirm the specifics with the building department at (518) 861-8554 before you rely on a figure.
Looking specifically at an accessory dwelling unit? See ADU rules for Altamont →
Zoning districts
| District | Min lot | Setbacks F / S / R | Max height | ADU |
|---|---|---|---|---|
| Business | 0.23 ac | 15 / 20 / 30 ft | 35 ft | Occupancy restricted |
| Central Business District | — | 0 / 0 / 50 ft | 35 ft | Occupancy restricted |
| Light Industrial | 0.23 ac | 40 / 12.5 / 20 ft | 35 ft | Occupancy restricted |
| Park | — | — | — | No |
| Planned Unit Development | — | — | — | — |
| Residential One Family - 10,000 Sq. | 0.23 ac | 20 / 10 / 30 ft | 35 ft | Occupancy restricted |
| Residential Multi-Family - 10,000 Sq. | 0.23 ac | 20 / 10 / 30 ft | 35 ft | No |
| Residential Professional Office | 0.23 ac | 20 / 10 / 30 ft | 35 ft | Special permit |
| Residential One Family - 15,000 Sq. | 0.34 ac | 20 / 15 / 30 ft | 35 ft | Special permit |
| Residential One Family - 20,000 Sq. | 0.46 ac | 25 / 15 / 30 ft | 35 ft | Special permit |
| Residential One Family - 40,000 Sq. | 0.92 ac | 35 / 25 / 50 ft | 35 ft | Special permit |
| Residential Conservation District | 0.92 ac | 35 / 25 / 50 ft | 35 ft | Special permit |
| Residential Senior Citizen | 0.23 ac | 20 / 10 / 30 ft | 35 ft | Occupancy restricted |
Business - The 15 ft front setback is a minimum, and there is a ceiling as well: a building may sit no farther back than 30 ft. At least 20% of the lot has to stay uncovered and pervious, separate from the building coverage cap.
- A two-family dwelling needs a lot of at least 0.344 acre.
- A building that combines business use with an apartment has a lot minimum of 0.115 acre.
Central Business District - The 5,000 square foot lot minimum applies to commercial and mixed use buildings only, and the district sets none for a residential building, so confirm a housing plan with the village before counting on one.
- The 25 ft lot width is a minimum, and a lot may be no more than 80 ft wide.
- The front setback is a range: a building is placed at the edge of the sidewalk, up to a maximum setback of 10 ft.
- Side yards are not required, since zero lot lines are permitted, but a side yard that is provided has to be 12.5 to 20 ft.
- An accessory building keeps 5 ft to a side lot line.
- The 50 ft rear yard is there to make room for parking behind the building.
- At least 10% of the lot has to stay uncovered and pervious.
Light Industrial - A two-family dwelling needs 0.459 acre here rather than the 0.23 acre lot minimum. At least 10% of the lot must also be left pervious, a separate requirement from the 40% building coverage cap.
- The 40 ft front yard is a minimum with no published maximum, so a building may sit further back.
Park - The Park district carries no dimensional standard of its own in this code, and it is not included in the density and dimensional requirements chart. That is by design rather than an omission.
- Since this district has no dimensional standard of its own, confirm with the building department which requirements and approval path apply before planning any construction here.
Planned Unit Development - A planned unit development requires at least 40 acres to create. Setbacks, coverage and other dimensions are not published in advance; they are set at the time the planned unit development is reviewed and approved under § 355-14.
- Confirm the standards that will apply to a specific project with the building department.
Residential One Family - 10,000 Sq. - The front yard is a band, 20 ft minimum and 30 ft maximum, so a house cannot sit further back than 30 ft. At least 50% of the lot must also be left pervious, a floor on uncovered ground separate from the 40% building coverage cap.
- A two-family dwelling needs 0.344 acre rather than 0.23 acre.
- A nonresidential use needs 0.918 acre.
- Senior housing takes a special use permit with site plan review, and then needs 6,000 sq ft of land per dwelling unit, with the pervious minimum dropping to 30%.
- An accessory building keeps 5 ft to the side lot line, not the 10 ft a house takes.
Residential Multi-Family - 10,000 Sq. - Multifamily is governed by land per unit: 6,000 sq ft of lot for each dwelling unit, alongside the 0.23 acre lot minimum. The front yard is a band as well, 20 ft minimum and 30 ft maximum.
- A two-family dwelling needs 0.344 acre rather than 0.23 acre.
- A nonresidential use needs 0.918 acre.
- Senior housing takes a special use permit with site plan review, on the same 6,000 sq ft of land per unit.
- At least 30% of the lot must be left pervious, a separate requirement from the 40% building coverage cap.
- An accessory building keeps 5 ft to the side lot line, not the 10 ft a house takes.
Residential Professional Office - The front yard is a band, 20 ft minimum and 30 ft maximum, so a house cannot sit further back than 30 ft. A two-family dwelling needs 0.344 acre rather than the 0.23 acre lot minimum.
- A professional office with an apartment is held to the same 0.23 acre lot minimum as a house.
- At least 10% of the lot must be left pervious, a separate requirement from the 40% building coverage cap.
- An accessory building keeps 5 ft to the side lot line, not the 10 ft a house takes.
Residential One Family - 15,000 Sq. - The front yard is a band, 20 ft minimum and 30 ft maximum. At least 50% of the lot must also be left pervious, a floor on uncovered ground separate from the 25% building coverage cap.
- A two-family dwelling needs 0.459 acre rather than the 0.344 acre lot minimum.
- A nonresidential use needs 0.918 acre.
Residential One Family - 20,000 Sq. - The front yard is a band, 25 ft minimum and 35 ft maximum. At least 50% of the lot must also be left pervious, a floor on uncovered ground separate from the 25% building coverage cap.
- A two-family dwelling needs 0.689 acre rather than the 0.459 acre lot minimum.
- A nonresidential use needs 0.918 acre.
Residential One Family - 40,000 Sq. - Elderly or senior housing and group family homes are allowed by special use permit with site plan review, and that route sets 6,000 square feet of land per dwelling unit, a 50 ft lot width, a 20 ft front setback and 40% building coverage.
- The 35 ft front setback is a minimum, and a building may sit no farther back than 50 ft.
- An accessory building keeps 10 ft to a side lot line, where a principal building takes 25 ft.
- A two-family dwelling needs a lot of at least 1.377 acres.
- Under that senior housing permit the side setback is 10 ft and the rear setback is 30 ft.
- At least 50% of the lot has to stay uncovered and pervious, separate from the building coverage cap.
Residential Conservation District - The front yard is a band, 35 ft minimum and 50 ft maximum. At least 50% of the lot must also be left pervious, a floor on uncovered ground separate from the 25% building coverage cap.
- A two-family dwelling needs 1.377 acres rather than the 0.918 acre lot minimum.
- An accessory building keeps 10 ft to a side lot line.
Residential Senior Citizen - Multifamily is governed by land per unit: 6,000 sq ft of lot for each dwelling unit, alongside the 0.23 acre lot minimum. The front yard is a band as well, 20 ft minimum and 30 ft maximum.
- A two-family dwelling needs 0.344 acre rather than 0.23 acre.
- A nonresidential use needs 0.918 acre.
- Senior housing takes a special use permit with site plan review, on the same 6,000 sq ft of land per unit.
- At least 30% of the lot must be left pervious, a separate requirement from the 40% building coverage cap.
Short-term rentals
No local short-term-rental law on record - which is not the same as permission. Altamont has no short term rental law of its own, so hosts answer to the 2025 New York State short term rental registry law. Confirm with the building department before counting on short term rental use of a home.
Conditions the code attaches:
- Registration under the New York State short term rental registry law applies even where no village rule does.
- The building department can be reached at (518) 861-8554.
Good to know
- UtilityNational Grid territory.
- Zoning codeVillage of Altamont Code, Chapter 355 (Zoning), with Attachment 1 (Use Schedule) and Attachment 2 (Density and Dimensional Requirements Chart)
- Building dept(518) 861-8554
- Last reviewed2026-09-20
Working out a budget? A standard-finish build here runs $202–$265/sq ft , and a conforming lot adds about $6,733 on top - see the full cost to build a house in Altamont, or what an ADU costs here.
Sizing up a specific parcel in Altamont?
Aldo pulls the exact zoning district, setbacks, and build feasibility for any parcel — before you buy. Enter your email to open Aldo and run your free report.
Other Albany County towns
All Albany County zoning: Albany (City) · Cohoes (City) · Watervliet (City) · Berne · Bethlehem · Coeymans · Colonie · Guilderland · Knox · New Scotland · Rensselaerville · Westerlo · Colonie (Village) · Green Island (Village) · Menands (Village) · Ravena (Village) · Voorheesville (Village)
Zoning figures for Village of Altamont are compiled from the municipal code (last reviewed 2026-09-20) and provided for decision-support only - not legal, engineering, or architectural advice. Setback and dimensional standards often carry conditions and exceptions; verify with the building department at (518) 861-8554 before relying on any number. Source: the Offsite / Aldo zoning dataset.